PSG Portal

Patient Safety Grid · Device 1 Pilot
Draft v3
Sep 2026
Discovery 25 Aug - 30 Sep 2026 · PS1 starts 1 Oct
DISCOVERY
PRE-PILOT
BANDING
GATE
25 Aug - 30 Sep PS1-PS5 · 1 Oct - 9 Dec ~1 Dec - 28 Dec ~6 Jan
Where are we?
Discovery phase — A2Z exploring reference-design hardware platforms. Pilot design doc, engagement tracker, and timeline delivered as drafts. Awaiting feedback and date confirmation before PS1 sprint begins 1 Oct.
8 milestones 62 deliverables 7 sprints ~6 Jan gate
What's next?
M1
HW platform locked
A2Z · PS1 · 14 Oct
M2
Pilot design signed off
A2Z + AyurVAID · PS1 · 14 Oct
M3
Round 1 built and tested
A2Z · PS3 · 11 Nov
What we need from AyurVAID
!
Review and sign off pilot design doc
A2Z + AyurVAID · By 14 Oct (M2)
!
Confirm pilot dates — banding start (~1 Dec), go/no-go (~6 Jan)
AyurVAID · Before PS1 starts (1 Oct)
!
Ward access for assessment — floor plans, beacon placement survey
AyurVAID ops · Two weeks before pilot start
!
Designate 3-5 nurses for usability validation session
AyurVAID · PS2-PS3 (Oct-Nov)
!
Patient consent protocol — admission workflow, consent forms, family app opt-in
AyurVAID legal/clinical · Before banding (~1 Dec)
!
MOU sign-off — commercial terms for pilot
AyurVAID + A2Z · PS4 (25 Nov)
!
Staff for training — 1-hour training sessions for ward nurses
AyurVAID nursing lead · PS5 (late Nov)

Overview

What, why, capabilities

Execution

Sprints, milestones, deliverables

Updates

Weekly status, RAG

Commercials

MOU, production